Example Asbestos Removal Projects in Paramount

The seven example jobs below are set in Paramount, Downey and Santa Fe Springs, from a manufactured home to a duplex. Each one lists what was sampled, what came out, the work days and an estimated cost.

Old vinyl and glue removed from a single-wide living room before new plank flooring

Example project

Home
1970s single-wide manufactured home in Paramount with carpet over sheet vinyl in the living room
Original request
Pull the carpet and lay new plank flooring
Testing
A Cal/OSHA-certified asbestos consultant samples the sheet vinyl and the glue beneath it at three spots
Found
Asbestos in the sheet vinyl and its glue
Area
About 150 sq ft of floor
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$2,600

Scope of work

Three samples, the district notice, the entry door and the room sealed with a filter running, the carpet lifted, the vinyl and glue removed wet, bagging and the haul. The clearance air test and the plank flooring are separate.

Project overview

In this example, the owner of a 1970s single-wide wants new plank flooring in the living room. When the carpet comes up, an old sheet vinyl is glued to the floor.

A manufactured home gets the same survey and notice rules as any other dwelling. The vinyl and its glue test positive, so the abatement crew removes them in two days, and the flooring installer comes after the air results.

The goal

The goal is a bare floor in the living room, so the new planks go down on a clean surface.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the vinyl at a lifted corner of the carpet.
  2. Before work The abatement contractor files the district notice online and the owner clears the room.
  3. Days one and two The room is sealed, the carpet is lifted and the vinyl and glue come up wet.
  4. Last An independent consultant tests the air before the installer starts.

Planning right

  • Move the sofa and the television out of the home.
  • Plan where to stay for the two work days.
  • Order the planks for after the air results.
  • Keep the lab report with the flooring invoice.

Get a free quoteMore about mobile and manufactured home removal

Ceiling texture removed from the hallway of a manufactured home

Example project

Home
1970s manufactured home in Paramount with a textured ceiling in the hallway and at both bedroom doors
Original request
Replace the hallway ceiling and add a new light
Testing
A Cal/OSHA-certified asbestos consultant samples the texture at three spots along the hall
Found
Asbestos in the ceiling texture
Area
About 110 sq ft of ceiling
Timeline
Notice no later than 10 working days ahead, then one working day
Cost
$1,700

Scope of work

Three samples, the district notice, the hallway sealed with a filter running, the texture soaked and scraped into bags, a HEPA clean and the haul. The clearance air test, the new ceiling panels and the light are separate.

Project overview

In this example, the owners of a 1970s manufactured home want a new ceiling and a light in the hallway between the two bedrooms.

The texture tests positive. The abatement crew removes it in a day with the hallway sealed, and the installer puts up the new ceiling after the air results.

The goal

The goal is a bare hallway ceiling, so the new panels and the light go up over a surface with nothing positive on it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceiling along the hall.
  2. Before work The contractor files the district notice online and the owners empty the hallway.
  3. Work day The hallway is sealed and the texture is soaked and scraped into bags.
  4. Last An independent consultant tests the air, then the installer is released.

Planning right

  • Take pictures and runners out of the hallway.
  • Plan to sleep elsewhere on the work day.
  • Hold the light fixture order until the air results.
  • Keep the lab report with the home papers.

Get a free quoteMore about popcorn ceiling removal

Tile and mastic removed from two bedroom floors

Example project

Home
1950s house in Downey with carpet over old tile in two bedrooms
Original request
Take up the carpet in both bedrooms and install new flooring
Testing
A Cal/OSHA-certified asbestos consultant samples the tile and mastic in each bedroom and the closet floors
Found
Asbestos in the tile and mastic in both bedrooms
Clear
The closet floors
Area
About 240 sq ft of floor
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$3,200

Scope of work

Samples from each room, the district notice, both bedrooms sealed with air filters running, the carpet lifted, the tile and mastic removed wet, bagging and the haul. The clearance air test and the new floor are separate.

Project overview

In this example, the owners of a 1950s house in Downey are replacing the carpet in two bedrooms. The carpet was laid over the original tile, which they only discover when a corner is lifted.

The tile and mastic test positive in both rooms and the closets are clear. The abatement crew works through the two bedrooms and leaves the closets alone.

The goal

The goal is bare subfloors in both bedrooms, so the new flooring is installed with no old mastic left.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples both bedrooms and the closets.
  2. Before work The contractor files the district notice online and the owners move the furniture out.
  3. Days one and two One bedroom at a time is sealed and the tile and mastic come up wet.
  4. Last An independent consultant tests the air before the new floor is ordered.

Planning right

  • Move beds and dressers into the living room.
  • Take the closet doors off their tracks.
  • Order the new floor after the air results.
  • Keep the lab report with the flooring contract.

Get a free quoteMore about floor tile and mastic removal

A whole house sampled before a rear addition is drawn

Example project

Home
1960s house in Santa Fe Springs where the owners plan a rear addition and a remodeled kitchen
Original request
Learn what is in the house before the addition is designed
Testing
A Cal/OSHA-certified asbestos consultant samples the ceilings, walls, floors and the rear wall where the addition joins
Found
Asbestos in the kitchen floor mastic and the compound on the rear wall
Clear
The ceilings and the other floors
Timeline
Samples, then lab results, then a written report
Estimated testing cost
$1,200

Scope of work

A visit by the consultant, samples from each room and the rear wall, a lab result for each and a written report that marks where each sample was taken. Removing the positive materials is priced on its own.

Project overview

In this example, the owners of a 1960s house plan a rear addition and a new kitchen. The addition will open the back wall and join the old floor framing.

The kitchen floor mastic and the compound on the rear wall test positive. The report records what was sampled and where, and the abatement crew is booked for those two materials before the builder opens the wall.

The goal

The goal is a written list of what is in the house before the addition is drawn, so the builder knows which materials to expect.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples each room and the rear wall.
  2. Results The lab reports each sample, with the mastic and the wall compound positive.
  3. Next The abatement crew is booked for those two materials.
  4. Then The builder opens the rear wall once they are out.

Planning right

  • Unlock the garage and the attic hatch.
  • Ask the consultant to list each room separately.
  • Give a copy of the report to the builder.
  • Keep the original with the house papers.

Get a free quoteMore about asbestos testing and surveys

Wall texture removed from a rented apartment bathroom between tenants

Example project

Home
1970s two-story apartment building in Paramount, with one upstairs unit empty
Original request
Redo the bathroom walls and ceiling before the next tenant
Testing
A Cal/OSHA-certified asbestos consultant samples the wall texture, the ceiling texture and the joint compound
Found
Asbestos in the wall texture
Clear
The ceiling texture and the joint compound
Area
About 70 sq ft of wall
Timeline
Less than 100 square feet of renovation, so no district notice, then one working day
Cost
$1,600

Scope of work

Plastic over the tub and the doorway, the wall texture removed wet, bagging, a cleanup and the haul. The survey, the clearance air test and the new wall finish are separate.

Project overview

In this example, the owner of a small apartment building is refreshing one upstairs bathroom between tenants. A unit in an apartment building is not a residential single-unit dwelling, so the survey comes first whatever the size of the job.

The wall texture tests positive and the ceiling and compound are clear. The abatement crew removes the texture in one day, and the painter finishes the bare walls.

The goal

The goal is bare bathroom walls in an empty unit, so the refresh is finished before the next tenant moves in.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the walls and ceiling of the empty unit.
  2. Results The wall texture is positive and the ceiling and compound are clear.
  3. Work day The bathroom is sealed and the wall texture is removed wet and bagged.
  4. Then The painter finishes the walls and the unit is listed.

Planning right

  • Pick a day when the unit is empty.
  • Take down the mirror and towel bars.
  • Tell the downstairs neighbors about the work day.
  • Keep the lab report with the building file.

Get a free quoteMore about drywall, joint compound and plaster removal

Duct wrap removed above a den that is becoming a bedroom

Example project

Home
1960s house in Paramount with a den that the owners are turning into a fourth bedroom
Original request
Add a supply vent and a return to the den
Testing
A Cal/OSHA-certified asbestos consultant samples the wrap on the duct junction above the den and the tape at its joints
Found
Asbestos in the wrap at the junction and in the tape
Timeline
Less than 100 square feet of asbestos-containing material removed, so no district notice, then one working day
Cost
$2,000

Scope of work

The attic hatch and vents sealed, wet removal of the wrapped junction and the taped joints into labeled bags, a cleanup and the haul. The survey, the clearance air test and the new vents are separate.

Project overview

In this example, a Paramount family is turning a den into a fourth bedroom. The heating crew has to cut into the duct junction above the den to add a supply vent and a return.

The wrap at the junction and its tape test positive. The abatement crew removes them first, so the heating crew works on bare duct.

The goal

The goal is a duct junction with the old wrap gone, so the new vents are cut into clean duct.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the junction from the attic hatch.
  2. Results The wrap and the tape are positive.
  3. Work day The attic is sealed and the wrapped junction is wetted, cut out and bagged.
  4. Then The heating crew adds the new vents.

Planning right

  • Clear the floor under the attic hatch.
  • Ask the heating crew to start after the abatement day.
  • Keep the lab report with the permit papers.
  • Plan to be without the heater for a day.

Get a free quoteMore about HVAC duct and pipe insulation removal

Ceiling, floor and wall materials removed from a duplex before it is torn down

Example project

Home
1950s one-story duplex in Paramount, two units, to be torn down for a new building
Original request
Demolish the duplex and clear the lot
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture, the floor tile and mastic, the wall plaster and the vent wrap in both units
Found
Asbestos in the ceiling texture, the floor tile and mastic and the wall plaster
Clear
The vent wrap
Area
About 1,800 sq ft of ceiling, floor and wall material
Timeline
Notice no later than 10 working days ahead, then six working days before the wrecking crew
Cost
$18,500

Scope of work

Samples from both units, the district notice, each unit sealed in turn with air filters running, the positive materials removed wet, bagging and the haul. The clearance air test, the wrecking and the lot cleanup are separate.

Project overview

In this example, the owner of a 1950s duplex is tearing it down for a new building. A demolition always needs the district notice, whatever the size of the building, and the survey comes before the wrecking crew.

Three materials test positive across both units. The abatement crew removes them before demolition, and the wrecking crew starts after the air results.

The goal

The goal is a duplex with the positive materials removed, so the wrecking crew works without them in the debris.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples both units.
  2. Before work The abatement contractor files the district notice online and the owner sets the demolition date after it.
  3. Days one to six Each unit is sealed in turn and the ceiling, floor and wall materials come out wet.
  4. Last An independent consultant tests the air, then the wrecking crew starts.

Planning right

  • Shut off the utilities with the utility companies.
  • Keep the district notice with the demolition permit papers.
  • Ask for a copy of the waste manifest when the job ends.
  • Schedule the wrecking crew only after the air results.

Get a free quoteMore about renovation and demolition abatement

Request a free asbestos removal quote

We recommend calling, but do feel free to contact us using this form. We'll get back to you with a free, personalized quote or additional questions as soon as possible. We're here to help.

Call (562) 635-8371

Call (562) 635-8371