Old vinyl and glue removed from a single-wide living room before new plank flooring
Example project
- Home
- 1970s single-wide manufactured home in Paramount with carpet over sheet vinyl in the living room
- Original request
- Pull the carpet and lay new plank flooring
- Testing
- A Cal/OSHA-certified asbestos consultant samples the sheet vinyl and the glue beneath it at three spots
- Found
- Asbestos in the sheet vinyl and its glue
- Area
- About 150 sq ft of floor
- Timeline
- Notice no later than 10 working days ahead, then two working days
- Cost
- $2,600
Scope of work
Three samples, the district notice, the entry door and the room sealed with a filter running, the carpet lifted, the vinyl and glue removed wet, bagging and the haul. The clearance air test and the plank flooring are separate.
Project overview
In this example, the owner of a 1970s single-wide wants new plank flooring in the living room. When the carpet comes up, an old sheet vinyl is glued to the floor.
A manufactured home gets the same survey and notice rules as any other dwelling. The vinyl and its glue test positive, so the abatement crew removes them in two days, and the flooring installer comes after the air results.
The goal
The goal is a bare floor in the living room, so the new planks go down on a clean surface.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the vinyl at a lifted corner of the carpet.
- Before work The abatement contractor files the district notice online and the owner clears the room.
- Days one and two The room is sealed, the carpet is lifted and the vinyl and glue come up wet.
- Last An independent consultant tests the air before the installer starts.
Planning right
- Move the sofa and the television out of the home.
- Plan where to stay for the two work days.
- Order the planks for after the air results.
- Keep the lab report with the flooring invoice.
Get a free quoteMore about mobile and manufactured home removal